CWL is constructing a solar power system totaling 13.25 MW DC on approximately 98 acres near Nestle Way and Great Dane Drive. This facility will generate an estimated 24,292 megawatt-hours of zero carbon emission energy during the first year of operation. Major equipment procurement began in early February of this year and is complete – receipt of major equipment has begun. Permits necessary at this time are in hand and construction crews are on site. Mechanical completion is scheduled for December 9, 2021 with final completion slated for February 3, 2022.